Judge Stark Issues Early Claim Construction Opinion

In Technology Innovations Associates v. Google, Inc., C.A. No. 13-0355-LPS (D. Del. Aug. 7, 2014), Chief Judge Leonard P. Stark recently construed a single term of the patents-in-suit – “sticky path” – having previously granted defendant’s request for early construction of this term.  The Court had agreed that this “proposed early, limited claim construction process would likely facilitate the just, speedy, and inexpensive determination of this action, even if the Court’s construction did not prove to be case dispositive.”  Id. at 1.  The Court adopted the plaintiff’s proposed construction, although the issue was a “close call.”  Id. at 6.